You can add a new production order manually for any item in production. When you add a new production order manually, all base data information that is associated with the selected item is automatically available in the new order, and you can change it if necessary. The and fields are blank when the order is first created. Select or enter the relevant information.
-
Click > .
-
On the tab, press CTRL+N to create a new order.
The form opens.
-
Select the item that you want to create a production order for in the field. Each item is associated with a BOM, (a list of component items that are used to produce the item), a route, and a sequence of operations that produce the finished product.
-
When the multisite functionality is activated, you must enter a value in the field. When you enter a site, the program displays a message asking whether to insert the active BOM version and the active route version that are associated with the site.
-
In the field, select whether the production type is or . (If the production type is , the production order is produced by a subcontractor.)
-
Enter the number of items that you want to produce in the field.
-
Select the delivery date from the calendar in the field, and enter the time that you want the production to be delivered.
-
Click OK.
The production order is listed with the status in the form.