In the following tables, you can see how the values of an estimate are distributed when the four different cost to complete methods are applied.

The first two tables contain the estimate assumptions and the last four tables are examples of estimates created in September where each example is created with one of the cost to complete methods.

Estimate assumptions

Estimate posted in August

Cost line

Transaction type

Forecasting

Actual

Cost to complete

Total

Development

Hour

Yes

70,000

30,000

100,000

Test

Hour

No

60,000

20,000

80,000

Subcontractor

Expense

Yes

25,000

5,000

30,000

Travel

Expense

No

10,000

2,000

12,000

Hardware

Item

No

80,000

0

80,000

Software

Item

Yes

35,000

7,000

42,000

280,000

64,000

344,000

Consumed cost in September

Cost line

Transaction type

Actual transactions in September

Forecast transactions in forecast model

Development

Hour

20,000

12,000

Test

Hour

16,000

5,000

Subcontractor

Expense

3,000

3,000

Travel

Expense

1,000

2,000

Hardware

Item

0

0

Software

Item

8,000

0

48,000

22,000

Cost to complete methods

The Total method:

Cost line

Transaction type

Forecasting

Actual

Cost to complete

Total

Development

Hour

Yes

90,000

10,000

100,000

Test

Hour

No

76,000

4,000

80,000

Subcontractor

Expense

Yes

28,000

2,000

30,000

Travel

Expense

No

11,000

1,000

12,000

Hardware

Item

No

80,000

0

80,000

Software

Item

Yes

43,000

-1,000

42,000

328,000

16,000

344,000

The Forecasting method

Cost line

Transaction type

Forecasting

Actual

Cost to complete

Total

Development

Hour

Yes

90,000

12,000

102,000

Test

Hour

No

76,000

5,000

81,000

Subcontractor

Expense

Yes

28,000

3,000

31,000

Travel

Expense

No

11,000

2,000

13,000

Hardware

Item

No

80,000

0

80,000

Software

Item

Yes

43,000

0

43,000

328,000

64,000

350,000

The As previous estimate method

Cost line

Transaction type

Forecasting

Actual

Cost to complete

Total

Development

Hour

Yes

90,000

12,000

102,000

Test

Hour

No

76,000

4,000

80,000

Subcontractor

Expense

Yes

28,000

3,000

31,000

Travel

Expense

No

11,000

1,000

12,000

Hardware

Item

No

80,000

0

80,000

Software

Item

Yes

43,000

0

43,000

328,000

20,000

348,000

The Set cost to complete to zero method

Cost line

Transaction type

Forecasting

Actual

Cost to complete

Total

Development

Hour

Yes

90,000

0

90,000

Test

Hour

No

76,000

0

76,000

Subcontractor

Expense

Yes

28,000

0

28,000

Travel

Expense

No

11,000

0

11,000

Hardware

Item

No

80,000

0

80,000

Software

Item

Yes

43,000

0

43,000

328,000

0

328,000