Work center properties are special attributes that you can assign to your work centers for use in the scheduling process. Properties are tied directly to the . For example, if you assign the property redto a paint machine on Monday, when you run the schedule, this work center will paint items red only on Mondays.

Note Note

Work center properties are not required when you set up calendars. However, if you want to use properties, it is more efficient to set them up at the same time.


  1. Select > > > .

  2. Press CTRL+N to create a new line.

  3. In the field, enter an alphanumeric identifier for the property.

  4. In the field, enter the name of the property.

    Note Note

    This is the final step to set up properties. If you want to add values to the properties, continue with step 5.


  5. Click .

  6. In the field, enter the name you assigned to that property in step 4.

  7. In the field, enter any additional information on the property.

See Also