Use this form to set up fundamental values in the system. The parameters are the lowest layer in the production system setup. They define how production order creation, estimates, scheduling, consumption feedback, and cost accounting should be handled.

There are two versions of this form.

You can define production parameters to apply on the company level in the form.

You can also define some of the production parameters to apply on the site level. Click > > to open the form.

When the multisite functionality is activated, the value that you set in the field determines whether the program uses the company-level parameters or the site-specific parameters. If you set the to site, the program uses the site-specific parameters where they are defined. If they are not defined, the program uses the company-level parameters.

If the multisite functionality is not activated, you can still enter site-specific parameters in the form. You might want to set up this information in advance to prepare for activating the multisite functionality. However, the site-specific parameters cannot be used until the multisite functionality is activated.

Navigating the form

The following tables provide descriptions for the controls in this form.

Tabs

Tab

Description

Enter the identification of the site.

Set up the parameters for higher level system functions. These include the method for calculating estimates, the profit-setting code to use when the sales price of the production order is defined, the reservations, and the kind of information to post to the ledger.

Define which settings should operate by default in each of the four journal types. For a more explicit definition of the types and their uses, see .

Apply these parameters when no other value is specified at a higher level, for example, when no journal name is specified for automatic picking.

Define settings to guide automatic updates of the production order as it moves through different production stages. The production order has a different status, depending on its stage. These settings determine that an update will be run when the production has passed a certain stage and is ready for the next. For example, the schedule will automatically be updated when a production has been cost-estimated and released.

Apply these parameters and select which inventory dimension elements to include in the listed journals and lines. Select the inventory dimensions in the pane. To select the table or journal on which the dimension is shown use the check boxes under .

Define the setup for production-relevant number sequences.

Fields

The third column in the following table indicates whether the particular parameter can be set only on the company level or also on the site level. Parameters that cannot be defined on the site level are not available to edit in the form.

Field

Description

Usage by company/site

Controls which production parameters are used when the multisite functionality is activated. The options are as follows:

- The company-wide parameters are always used. This is the only option that is available when the multisite functionality is not activated.

- The parameters for the selected site are used. If no site parameter is defined, the program uses the parameter that is defined for the company. This option is available only when the multisite functionality is activated.

Not applicable

The profit-setting used in determining sales price.

Company

Select when auto-reservation should be performed.

Company

Determines how production should be posted to ledger.

Company

The maximum number of times the job scheduling should try to solve conflicts that result from capacity overload.

Company/site

The maximum job lead time in days.

Company/site

Select the check box to enable manually setting the next operation number in routes.

Company

When you select this field, you must enter a validity period for a route that states when it is valid. When the starting date expires, the route is no longer valid.

Company

When you select this field, you cannot change the status of a route once it has been approved.

Company

When you select this field, you cannot edit a route.

Company

Select the check box to enable posting picking lists in the ledger.

Company/site

Select the check box to enable posting production orders that are reported–as–finished in the ledger.

Company/site

Select the check box to exclude the transaction type from ledger transactions when they are totaled and created during production posting.

Company/site

Select the check box to include capacity that is reserved for planned orders during production scheduling.

Company/site

Select the check box to include capacity that is reserved for projects during production scheduling.

Company/site

Use this field to improve the performance of the job scheduling. When you select this check box, the program searches for the first work center that fulfills the required date and time. If you do not select the check box, the program searches for the work center that fulfills the required date and time and, also, the shortest lead time.

Company/site

Select this field if you want to calculate the estimated cost price for a production order during the estimation stage. You can see the results in the form. The realized cost price of a production order is calculated when you post production journals, regardless of this parameter.

Company/site

Select the check box to delete capacity reservations when reporting production orders as finished.

Company/site

Select the check box to use the estimated cost price to determine the physical value when reporting production orders as finished.

Company/site

The default journal name that is used if nothing else is entered for the production order line.

Company/site

The default journal name that is used if nothing else is entered for the production order line.

Company/site

The default journal name that is used if nothing else is entered for the production order line.

Company/site

The default journal name that is used if nothing else is entered for the production order line.

Company/site

Select the check box to enable specifying a quantity category in route and job card journals.

Company/site

Select the check box to enable specifying an hour category in route and job card journals.

Company/site

Select this field to enable automatic consumption when you update a production order. The program then posts the picking list for the consumed materials. The options are the following:

  • – Automatically register consumption according to the setting of the field on the BOM line.

  • – Always register automatic consumption.

  • – Do not register automatic consumption.

Note Note

This setting is used when you update a production order but do not directly access the or forms.


Company

Select the check box to enable feedback for the last operation to be automatically reported–as–finished.

Company

Select the check box to enable automatic update of the capacity plan when posting journals.

Company/site

Select the check box to allow negative picking in the physical inventory when posting.

Company

Select the check box to automatically reduce item consumption to the physical inventory when the stock is out.

Company

Select the check box for the planned order quantity to appreciate the attached inventory transactions.

Company

Accept missing feedback for work center and item consumption.

Company

Select the check box to set BOM consumption for the current production to be automatically picking–list updated.

Company

Select the method for posting item and work center consumption that is used for the error–reported quantity.

Company/site

Account number

Use this (AccountNum) to the define length and adjustment of the ledger account. Alphanumeric characters are allowed.

  1. Enter the length of the longest possible ledger account number.

  2. Select between left adjusted and right adjusted.

    Note Note

    The adjustment type is important for the sorting of the accounts in Chart of accounts.


Company/site

Select the check box to ensure that scheduling observes capacity limitations.

Company/site

Select the check box to ensure that scheduling makes sure (by use of futures messages) that materials are available.

Company/site

Select the check box to ensure that scheduling observes any property requirements.

Company/site

Select the method to use for automatic scheduling.

Company/site

Select an option to set up automatic BOM consumption when you update a production order. The program then posts a picking list journal for the received quantity on the purchase order. The options are:

  • – Automatically register consumption according to the setting of the field on the BOM line.

  • – Always register automatic consumption.

  • – Do not register automatic consumption.

Note Note

This setting is used when you update a production order but do not directly access the or forms.


Company/site

Select an option to set up automatic BOM consumption when production orders are updated automatically to the Start phase. The program then posts a picking list journal for the consumed materials. The options are:

  • – Automatically register consumption according to the setting of the field on the BOM line.

  • – Always register automatic consumption.

  • – Do not register automatic consumption.

Company/site

Select an option to set up automatic route consumption when production orders are updated automatically to the Start phase. The options are:

  • – When a purchase order is received physically, a connected operation is updated by posting a route card journal. The route group from the operation determines whether the setup times or process times are consumed in the journal.

  • – When a purchase order is received physically, a connected operation is updated by posting a route card journal. Setup times and process times are always consumed regardless of the automatic route consumption settings of the route group.

  • – When a purchase order is received physically, a connected operation is not updated.

Company/site

Select an option to set up automatic BOM consumption when production orders are updated automatically to the Report as finished phase. The program then posts a picking list journal for the consumed materials. The options are:

  • – Automatically register consumption according to the setting of the field on the BOM line.

  • – Always register automatic consumption.

  • – Do not register automatic consumption.

Company/site

Select an option to set up automatic route consumption when production orders are updated automatically to the Report as finished phase. The options are:

  • – When a purchase order is received physically, a connected operation is updated by posting a route card journal. The route group from the operation determines whether the setup times or process times are consumed in the journal.

  • – When a purchase order is received physically, a connected operation is updated by posting a route card journal. Setup times and process times are always consumed regardless of the automatic route consumption settings of the route group.

  • – When a purchase order is received physically, a connected operation is not updated.

Company/site

Select the check box to group purchases by vendor when purchases are automatically created during estimation.

Company

Select the check box to group purchases by combination of vendor and buyer group when purchases are automatically created during estimation.

Company

Select the method for registering automatic route consumption. The options are the following:

  • – When a purchase order is received physically, a connected operation is updated by posting a route card journal. The route group from the operation determines whether setup or process times are consumed in the journal.

  • – When a purchase order is received physically, a connected operation is updated by posting a route card journal. Setup and process times are always consumed regardless of the automatic route consumption settings of the route group.

  • – When a purchase order is received physically, a connected operation is not updated.

Company/site

Select the check box if you want to be informed about route–card–journal posting when a purchase order is received physically.

Company/site

Select the check box to display the dimension in the list along with productions.

Not applicable

Select the check box to display the dimension in the list along with production lines.

Not applicable

Select the check box to display the dimension in the list of the production picking list journal.

Not applicable

Select the check box to display the dimension in the list of the productions in the reported–as–finished journal.

Not applicable

Select the number sequence codes to use when production transactions are created.

Company

Should the reference follow another reference?

Company