This master scheduling scenario involves the following conditions:
-
The multisite functionality is activated. Therefore, the site dimension is mandatory and must be entered on the demand transaction.
-
The warehouse dimension is not set to mandatory. The warehouse may be known, but it is not used in the master scheduling calculation.
-
The site dimension is set for coverage planning. Other dimensions may be set for coverage planning also. However, they are not affected by the multisite functionality.
-
The warehouse dimension is not set for coverage planning. Therefore, supply and demand are aggregated by site (and perhaps other coverage-planned dimensions also).
The following graphic illustrates how the master scheduling proceeds. The parameters that are referred to in the graphic, and their locations, are as follows:
-
Item coverage is defined for the item. Click > . Select the item and then click > .
-
Refill relations are defined for the warehouse. Click > > > . On the tab, see the field group.
-
BOM is set to Stop explosion. Click > , and then select the BOM. Click the tab and see the field.