Use this form to create and define work center groups to help manage production. Work center groups have to be set up before creating work centers. Work centers with similar functions in the production process are usually assigned to the same work center group. The parameters for the group are the default parameters for each work center in this group. This eliminates the need to define parameters for each work center individually.
It is better not to change work center groups after they are created unless you want to make changes to their specific characteristics. However, you can make changes to individual work centers at any time, without these changes affecting the characteristics assigned to the group as a whole.
More on scheduling
Capacity load is placed on the work center group during operation scheduling and on the individual work centers during job scheduling. When you run job scheduling, the application will examine all possible work center combinations and select the one with the shortest lead time. Depending on the number of work centers, this could affect performance. There can be a maximum of 32 work centers involved in the scheduling of one operation. If you exceed this number, an message appears.
Tasks that use this form
Navigating the form
The following tables provide descriptions for the controls in this form.
Tabs
Tab |
Description |
||
---|---|---|---|
Create and view work center groups and their types, names, and associated calendars. |
|||
View or edit general information for the selected work center group. Each work center group can be assigned a different type. For example, if the jobs or operations are performed by an external work center (subsupplier), select . In this case, you will have to assign a vendor account number to the work center group. If there is no account number, the application will not reserve capacity, even though the time planned for the vendor to conduct the work will already be calculated as production time in scheduling.
|
|||
|
Assign issue and receipt accounts for work in progress (WIP). |
||
|
Assign routing groups to the work center group. The routing group determines the methods for calculating records and schedules and for handling feedback. You can also assign cost categories, which control financial transactions that are associated with the work center groups. |
||
|
Enter the values for calculating production times in the selected work center group. You can override the times on the route, production route, and individual work center. |
||
|
View the creation date of the work center group and the number of work centers it contains. |
||
View the department, cost center, and purpose for the selected work center group. |
Buttons
Fields
Field |
Description |
||
---|---|---|---|
|
Unique identification of the work center group. |
||
|
Select the warehouse that you want to assign to the work center group.
|
||
|
Select the location in the warehouse for the work center group.
|
||
|
Select from the following work center types: |
||
|
Work center name. |
||
|
Select the calendar to use for scheduling. |
||
|
Work center or work center group to be assigned. |
||
|
Select a vendor from the drop-down list if the work center type is . |
||
|
Efficiency percentage that applies to the work center. |
||
|
Maximum percentage of daily capacity to be operations-scheduled per production. |
||
|
Specify if the work center operates with limited capacity. |
||
|
Select the check box to define the current work center group as a bottleneck resource. A bottleneck resource is scheduled by using finite capacity when the field and the field on the form are selected. |
||
|
Capacity per hour in capacity unit. |
||
|
Unit the capacity is measured in. |
||
|
Select the issue account for work in process. For more information, see the field in Production orders (form). |
||
|
Select the receipt account for work in process. For more information, see the field in Production orders (form). |
||
|
Select the account that is used to credit work in process for costing. For more information, see the field in Production orders (form). |
||
|
Select the account that is used to debit work in process for costing. For more information, see the field in Production orders (form). |
||
|
Specify a default route group to use when you select a work center group during the creation of an operation relation. |
||
|
Proposed value for scrap of jobs that are processed for the group. |
||
|
Task group for searching for alternatives. |
||
|
Enter a minimum requirement for searching for alternative work centers. |
||
|
The cost category proposal for setup time. |
||
|
The cost category for process time. |
||
|
The cost category for quantity. |
||
|
Queue time before value proposed for jobs that are processed for the group. |
||
|
Proposed value for setup time of jobs that are processed for the group. |
||
|
Proposed value for production time of process quantity. |
||
|
Proposed value for quantity that can be produced in run time. |
||
|
Proposed value for transit time to next work center. |
||
|
The time that the items have to wait after the operation is finished before the next operation can start. |
||
|
Conversion factor to hours. (Factor X Time) = Time in hours. |
||
|
Quantity that can be moved between sequential work centers. |
||
|
Work center setup or creation date. |
||
|
Number of work centers included in the group. |
||
|
Specify a department dimension. For more information, see Dimensions. |
||
|
Specify a cost center dimension. For more information, see Dimensions. |
||
|
Specify a purpose dimension. For more information, see Dimensions. |